CONTRACT NO: HY/2019/14
 
New Wang Tong River Bridge

 

Under Environmental Permit no. EP-555/2018/A
 
Quarterly Environmental Monitoring & Audit Report
 
july - september 2022


CLIENTS:

PREPARED BY:

 

Highways Department

 

 

 

 

Lam Environmental Services Limited

 

19/F Remex Centre,

42 Wong Chuk Hang Road,

Hong Kong

 

 

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

Certified by:



 

 

 

 

________________________________

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

   October 2022

 

 


Table of contents

 

1     Introduction.. 9

1.1.......... Scope of the Report 9

1.2.......... Structure of the Report 9

2     Project Background.. 10

2.1.......... Background. 10

2.2.......... Project Organization and Contact Personnel 10

2.3.......... Construction Activities. 11

3     Status of Regulatory Compliance.. 12

3.1.......... Status of Environmental Licensing and Permitting under the Project 12

3.2.......... Status of Submission under the EP-555/2018/A.. 12

3.3.......... Status of Submission under the EP-555/2018/A.. 13

4     Monitoring Requirements.. 14

4.1.......... Noise Monitoring. 14

4.2.......... Air Monitoring. 15

4.3.......... Water Quality Monitoring. 17

5  Monitoring Results.. 199

5.1.......... Noise Monitoring Results. 199

5.2.......... Air Monitoring Results. 199

5.3.......... Water Quality Monitoring Results. 199

5.4.......... Waste Management 25

6     Compliance Audit.. 27

6.1.......... Noise Monitoring. 27

6.2.......... Air Quality Monitoring. 27

6.3.......... Water Quality Monitoring. 27

6.4.......... Summary of Exceedance. 32

6.5.......... Environmental Site Audit 32

6.6.......... Review of the Reasons for and the Implications of Non-compliance. 32

6.7.......... Summary of action taken in the event of and follow-up on non-compliance  32

7     Complaints, Notification of Summons and Prosecution.. 33

8     Conclusion.. 34


lIST OF TABLES

 

Table 2.2       Contact Details of Key Personnel

Table 3.1       Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Table 3.2       Summary of submission status under EP-555/2018/A

Table 4.1       Noise Monitoring Station

Table 4.3       Action and Limit Level for Noise Monitoring

Table 4.4       Air Monitoring Station

Table 4.6       Action and Limit Level for Air Quality Monitoring

Table 4.7     Marine Water Quality Stations for Water Quality Monitoring

Table 4.9       Action and Limit Level for Water Quality Monitoring

Table 5.1       Summary of Quantities of Inert C&D Materials

Table 5.2       Summary of Quantities of C&D Wastes

Table 8.1       Cumulative Statistics on Complaints

Table 8.2       Cumulative Statistics on Successful Prosecutions

 

 

lIST OF FIGUREs

 

Figure 2.1     Project Layout

Figure 2.2     Project Organization Chart

Figure 4.1    Locations of Noise Monitoring Station

Figure 4.2    Locations of Air Quality Monitoring Stations

Figure 4.3    Locations of Water Quality Monitoring Stations

 

 

 

lIST OF APPENDIces

 

Appendix 3.1    Implementation Schedule

Appendix 4.1    Action and Limit Level

Appendix 4.3    Wind data extracted fro HKO Automatic Weather Station

Appendix 5.2    Noise Monitoring Results and Graphical Presentations

Appendix 5.3    Air Quality Monitoring Results and Graphical Presentations

Appendix 5.4    Water Quality Monitoring Results and Graphical Presentations

Appendix 6.1    Event and Action Plans

Appendix 6.2    Summary for Notification of Exceedance

Appendix 8.1    Complaint Log


EXECUTIVE SUMMARY

       i.        This is the Environmental Monitoring and Audit (EM&A) Quarterly Report – July 2022 to September 2022 of New Wang Tong River Bridge under Environmental Permit no. EP-555/2018/A (Hereafter as “the Project”). The construction works of the Project was commenced on 12 July 2021 and the tentative completion date is Q3 2024. This is the 5th Quarter EM&A report presenting the environmental monitoring findings and information recorded during the period of 01 July 2022 to 30 September 2022.

 

      ii.        In the reporting month, the principal work activities conducted are as follow:

July 2022

August 2022

September 2022

·    Pilling construction

·    Pile loading test

·    Piling construction

·    Excavation works

·    Excavation works

 

 

Air Quality Monitoring

     iii.        1-hour and 24-hour Total Suspended Particulates (TSP) monitoring was conducted at two monitoring station. 24-hour TSP shall be sampled at least once in every 6 days, while sampling for 1-hour TSP shall be at least 3 times in every 6 day in the reporting period.

     iv.        No action or limit level exceedance was recorded in this reporting period.

 

Noise Monitoring

      v.        Noise monitoring was conducted at one noise monitoring station once per week in the reporting period.

     vi.        No action or limit level exceedance was recorded in this reporting period.

 

Water Quality Monitoring

    vii.        Water quality monitoring was conducted at seven monitoring stations three days per week in according to the schedule in the reporting period. Details of water quality monitoring results and graphical presentation can be referred in Appendix 5.4.

   viii.        Owing to accessibility and safety issues, water quality monitoring at Station W3 was cancelled with verification from the IEC in November 2020 and approval from the EPD in December 2020.

     ix.        Action level exceedance on turb was recorded at station W1 during mid-flood on 6 July 2022.  Investigation revealed this exceedance could be due to: Localized fluctuation in water quality due to no exceedances recorded at W4 downstream to construction site before W1; no unauthorized discharge or muddy plume observed.

      x.        Action level exceedance on turb was recorded at station W2 during mid-flood on 6 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation in water quality due to no exceedances recorded at W4 downstream to construction site before W2; no unauthorized discharge or muddy plume observed.

     xi.        Action level exceedance on turb and limit level of SS were recorded at station W5 during mid-ebb on 6 July 2022. Investigation revealed this exceedance could be due to: High turbidity and SS recorded at upstream control station W4 (Turb: 24.8NTU, SS:19.0 mg/L) stirred up downstream riverbed during tidal flush.

    xii.        Action level exceedance on DO was recorded at station W2 during mid-flood on 15 July 2022.  Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

   xiii.        Action level exceedance on DO was recorded at station W4 during mid-flood on 15 July 2022.  Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

   xiv.        Action level exceedance on DO was recorded at station W1 during mid-flood on 18 July 2022.  Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

    xv.        Action level exceedance on DO was recorded at station W4 during mid-flood on 18 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

   xvi.        Action level exceedance on DO was recorded at station W8 Surface during mid-ebb on 20 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

  xvii.        Action level exceedance on DO was recorded at station W1 during mid-flood on 22 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

 xviii.        Action level exceedances on DO and turb were recorded at station W2 during mid-flood on 25 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed; Localized fluctuation in water quality due to no exceedances recorded at W4 downstream to construction site before W2; no unauthorized discharge or muddy plume observed.

   xix.        Action level exceedance on DO was recorded at station W4 during mid-flood on 25 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

    xx.        Action level exceedance on DO was recorded at station W7 during mid-ebb on 25 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

   xxi.        Action level exceedance on DO was recorded at station W8 Surface during mid-ebb on 25 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

  xxii.        Action level exceedance on DO was recorded at station W2 during mid-flood on 27 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

 xxiii.        Action level exceedances on DO and turb were recorded at station W4 during mid-flood on 27 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed; Localized fluctuation around baseline turb range; unlikely contributed by solid materials from construction works; extremely high water level observed during monitoring.

xxiv.        Action level exceedance on DO was recorded at station W7 during mid-ebb on 27 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

 xxv.        Action level exceedance on DO was recorded at station W8 Surface during mid-ebb on 27 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

xxvi.        Action level exceedance on DO was recorded at station W8 Bottom during mid-ebb on 27 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

xxvii.        Action level exceedances on DO and turb were recorded at station W2 during mid-flood on 29 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed; Localized fluctuation around baseline DO range; no river channel blockage was observed; Relatively higher turbidity recorded at upstream control station W4 (Turb: 12.1 NTU) whereas no SS exceedance recorded; unlikely contributed by solid materials from construction works.

xxviii.        Action level exceedances on DO, turb and SS were recorded at station W4 during mid-flood on 29 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed; Localized fluctuation around baseline turb and SS range; extremely high water level observed during monitoring and SS could be contributed by turbulance stirring up riverbed precipitate during tidal flush; unlikely contributed by solid materials from construction works.

xxix.        Action level exceedance on DO was recorded at station W7 during mid-ebb on 29 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

 xxx.        Action level exceedance on DO was recorded at station W8 Bottom during mid-ebb on 27 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed

xxxi.        Limit level exceedance on SS was recorded at station W5 during mid-ebb on 5 Aug 2022.  Investigation revealed this exceedance could be due to: Relatively high SS recorded at upstream control station W4 (SS:14.0 mg/L); Muddy water discharging from upstream control station W4 and rain water disturbing the river water current may increase the downstream SS level at downstream monitoring station W5.

xxxii.        Action level exceedance on DO and Turb were recorded at station W1 and W2 during mid-flood on 12 Aug 2022. Investigation revealed these exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed; Cloudy water may be the cause of the increase of turb level; unlikely contributed by solid materials from construction works.

xxxiii.        Action level exceedance on DO were recorded at station W2 and W8 Bottom during mid-flood and mid-ebb respectively on 15 Aug 2022. Investigation revealed these exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

xxxiv.        Action level exceedance on DO were recorded at station W1, W4 during mid-flood and W7 during mid-ebb on 22 Aug 2022. Investigation revealed these exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

xxxv.        Action level exceedance on DO were recorded at station W4 and W8 Bottom during mid-flood and mid-ebb respectively on 26 Aug 2022. Investigation revealed these exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

xxxvi.        Action level exceedance on DO were recorded at station W6, W7, W8 Surface and W8 Bottom during mid-ebb on 29 Aug 2022. Investigation revealed these exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

xxxvii.        Action level exceedance on DO was recorded at station W7 during mid-ebb on 31 Aug 2022. Investigation revealed these exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

xxxviii.        Action level exceedances on DO was recorded at station W2 and W4 during mid-flood on 5 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

xxxix.        Action level exceedance on SS was recorded at station W7 during mid-ebb on 5 Sep 2022. Investigation revealed this exceedance could be due to: High waves was observed at near shore sampling location W7 during mid-ebb. Water current may stir up the sea shore and sea bed sediment and cause the exceedance.

     xl.        Action level exceedances on DO was recorded at station W2 and W4 during mid-flood on 7 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

    xli.        Action level exceedances on DO was recorded at station W5, W6, W7 and W8 Surface during mid-ebb on 7 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

   xlii.        Action level exceedances on DO was recorded at station W1, W2 and W4 during mid-flood on 9 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

  xliii.        Limit level exceedance on SS was recorded at station W1 during mid-flood on 9 Sep 2022. Investigation revealed this exceedance could be due to: Special localized extreme water quality due to no Turb or SS exceedances recorded before W1; muddy river water flow was observed at the upper end of the river after W2 during mid-flood may cause the exceedance of SS at W1.

  xliv.        Action level exceedances on DO was recorded at station W5, W6, W7, W8 Surface and W8 Bottom during mid-ebb on 9 Sep 2022. . Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

   xlv.        Action level exceedances on DO was recorded at station W2 and W4 during mid-flood on 13 Sep 2022. Action level exceedances on Turb was recorded at station W6 during mid-ebb on 13 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO and water quality range; no river channel blockage was observed; no muddy water was observed; no discharge or water leakage from the construction site was observed.

  xlvi.        Limit level exceedances on Turb was recorded at station W5, W6, W7 and W8 Surface during mid-ebb on 15 Sep 2022. Investigation revealed this exceedance could be due to: Extreme low water level was observed from the upstream; yellow-ish pigment was observed during mid-ebb at the open water (from W5 to W8); no discharge or leakage from the construction site was found.

 xlvii.        Limit level exceedances on Turb was recorded at station W5 during mid-ebb on 17 Sep 2022. Investigation revealed this exceedance could be due to: Yellow-ish pigment from the previous event was still observed and accumulated at shallow water area (W5); no discharge or leakage from the construction site was found.

xlviii.        Action level exceedances on DO at W1 and W4; action level exceedance on Turb at W2; limit level on SS at W4 was observed during mid-flood on 19 Sep 2022. Action level on Turb and limit level on SS was recorded at W6 during mid-ebb on 19 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed; significant amount of foams was observed at near-shore areas and may cause the exceedance for Turb and SS; no discharge or water leakage from the construction site was observed.

  xlix.        Action level exceedances on DO was recorded at station W2 and W7 during mid-flood and mid-ebb respectively on 21 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

       l.        Action level exceedance on DO was recorded at station W8 Bottom during mid-ebb on 26 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

      li.        Action level exceedance on SS was recorded at station W8 Bottom during mid-ebb on 28 Sep 2022. Investigation revealed this exceedance could be due to: Strong monsoon signal was on and the strong wind may produce strong under-surface current which stir up the sediment at the sea floor, causing slightly high SS level at W8 Bottom.

 

Site Inspections and Audit

     lii.        During the reporting period, the Environmental Team (ET) conducted weekly site inspections and monthly landscape site inspections and IEC attended the joint site inspection monthly.

    liii.        No non-compliance was found during the site inspection while reminders on environmental measures were recommended.

 

Complaints, Notifications of Summons and Successful Prosecutions

    liv.        No environmental complaint, notification of summons and successful prosecution regarding the construction works was recorded in the reporting period.

 

Reporting Changes

     lv.        There are no particular reporting changes.

 

1          Introduction

1.1          Scope of the Report

1.1.1.     Lam Environmental Services Limited (LES) has been appointed to work as the Environmental Team (ET) under Environmental Permit (EP) no. EP-555/2018/A to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for New Wang Tong River Bridge (Register No.: AEIAR-199/2016).

1.1.2.     According to Section 10.6 of the Project EM&A Manual, the Quarterly EM&A Report should be submitted.

1.2          Structure of the Report

Section 1        Introduction – details the scope and structure of the report.

 

Section 2        Project Background – summarizes background and scope of the project, site description, and project organization and contact details of key personnel during the reporting period.

 

Section 3        Status of Regulatory Compliance – summarizes the status of valid Environmental Permits / Licenses during the reporting period.

 

Section 4        Monitoring Requirements – summarizes all monitoring parameters, monitoring criteria and respective event and action plan.

 

Section 5        Monitoring Results – summarizes the monitoring results obtained in the reporting period.

 

Section 6        Compliance Audit – summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 7        Environmental Site Audit – summarizes the findings of weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.

 

Section 8        Complaints, Notification of summons and Prosecution – summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 9        Conclusion

2          Project Background

2.1          Background

2.1.1.     Silver Mine Bay is a popular bathing beach in Mui Wo, Lantau that attracted 4,550 visitors on a peak day and over 69,000 visitors utilized the beach in 2012.

2.1.2.     In order to relieve the overcrowding problem and the road safety concern of Wang Tong Bridge (hereafter called “Old Bridge”), two bridges (pedestrian bridge and cycle bridge) are proposed to replace the Old Bridge. The new pedestrian bridge and the new cycle bridge (hereafter called “New Bridge”) are also designed to align with the future amenity development on the northern side of the Old Bridge. The location of the project site is shown in Figure 2.1.

2.1.3.     The Project consists of a designated project under Part I, Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO) which is Item C.12 – (a)…a dredging operation which is less than 500m from the nearest boundary of an existing…(iii) bathing beach…

2.1.4.     The major components of the Project under Environmental Permit (EP) (EP No. EP-555/2018/A) comprises: (i) demolition of the existing Wang Tong River Bridge; and (ii) construction of a new twin bridge with segregation for pedestrians and cyclists.

 

2.2          Project Organization and Contact Personnel

2.2.1       Highways Department is the overall project controllers for the Project. For the construction phase of the Project, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.2.2       The project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are summarized in Table 2.2:


Table 2.2             Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

Highways Department (HyD)

The Engineer for the Contract

Senior Engineer

Mr. Terry Chung

3903 6799

3188 3418

Engineer’s Representative

Engineer

Mr. Yeung Sui Chung

3903 6813

3188 3418

Unison Construction Engineering Limited

Contractor

Site Agent

Mr. Peter Lui

2690 2232

2363 3199

Environmental Officer

Ms. Suki Chan

ANewR Consulting Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. James Choi

2618 2831

3007 8648

Lam Environmental Services Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

2.3          Construction Activities

2.3.1       In the reporting period, the principal work activities conducted are as follows.

July 2022

August 2022

September 2022

·    Pilling construction

·    Pile loading test

·    Piling construction

·    Excavation works

·    Excavation works

 

 

2.3.2       Overall layout showing work areas is shown in Figure 2.1.

 

3          Status of Regulatory Compliance

3.1          Status of Environmental Licensing and Permitting under the Project

3.1.1.     A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.1.

Table 3.1 Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licences

Permit. No. / Account No.

Valid From

Expiry Date

Status

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

Form NA submitted to EPD on 25 June 2021.

Environmental Permit

EP-555/2018/A

16 Dec 2020

N/A

Valid

Billing Account for Disposal of Construction Waste

7038550

29 Mar 2021

End of the Project

Valid

Registration as a Chemical Waste Producer

5213-962-U2333-01

28 Jun 2021

N/A

Valid

Discharge Licence

WT00040069-2021

10/1/2022

31/1/2027

Valid

Construction Noise Permit

N/A

 

3.2          Status of Submission under the EP-555/2018/A

3.2.1.     A summary of the current status on submission under EP-555/2018/A is shown in Table 3.2.

Table 3.2 Summary of submission status under EP-555/2018/A

EP Condition

Submission

Date of Latest Submission^ or Approval#

Condition 1.12

Notification of Commencement Date of Works

3 June 2021 ^

Condition 2.7

Submission of Management Organization of Main Construction Companies, the ET and the IEC

20 May 2021 ^

Condition 2.8

Submission of Construction Works Schedule and Location Plan

22 June 2021 #

Condition 2.9

Submission of Breeding Bird Survey Report

29 December 2020 #

Condition 3.3

Submission of Baseline Monitoring Report

24 June 2021 #

Condition 4.2

Setting up Dedicated Internet Website

28 April 2021 ^

 

 

3.3          Status of Submission under the EP-555/2018/A

3.3.1       Mitigation measures according to the environmental mitigation implementation schedule and the EIA were generally implemented by the Contractor as listed and shown in Appendix 3.1.

 

 

4          Monitoring Requirements

4.1          Noise Monitoring

Noise Monitoring Stations

4.1.1.     The noise monitoring stations for the Project are listed and shown in Table 4.1 and Figure 4.1.

Table 4.1 Noise Monitoring Station

Monitoring Station ID

Monitoring Location

Measurement Type

Level (in terms of no. of floor)

NMS1 A

1 Tung Wan Tau Road

Free-field

G/F

 

Remarks A:    As discussed with the lot owner, a fine adjustment of location at the boundary of 1 Tung Wan Tau Road was proposed and approved in the Baseline Monitoring Report, in order to prevent access obstruction.

 

Noise Monitoring Parameters, Frequency and Duration

4.1.2.     For daytime construction work on normal weekdays (0700-1900 Monday to Saturday), one set of 30-min measurement shall be carried out at each NMS every week. Measurement procedures shall be referred to the Noise Control Ordinance-TM. Construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq 30min shall be used as the monitoring parameter. As supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

 

EVENT and action plan

4.1.3.     Noise Standards for Daytime Construction Activities are specified under EIAO-TM. The Action and Limit levels for construction noise are defined in Table 4.3 and Appendix 4.1. Should non-compliance of the criteria occurs, action in accordance with the Event and Action Plan in Appendix 6.1 shall be carried out.

 

Table 4.3 Action and Limit Level for Noise Monitoring

Monitoring Station

Action Level

Limit Level

NMS1

When one documented complaint is received

75 dB(A)

 


4.2          Air Monitoring

Air Quality Monitoring Stations

4.2.1.     The air monitoring stations for the Project are listed and shown in Table 4.4 and Figure 4.3.

Table 4.4 Air Monitoring Station

Monitoring Station

Location

Level (in terms of no. of floor)

AMS1 A

Silvermine Beach Resort

G/F

AMS2 B, C

1 Tung Wan Tau Road

G/F

Remarks A:    AMS1 recommended under EM&A manual is at the north of boundary wall of Silvermine Beach Resort. Positioning of HVS on a narrow road at the northern boundary wall would obstruct access of passengers. After liaison with the resort owner, HVS is located near the eastern boundary wall, which is representative and suitable for air quality monitoring. Thus, fine adjustment of location at the boundary of Silvermine Beach Resort was therefore proposed and approved in the Baseline Monitoring Report.

 

Remarks B:    As discussed with the lot owner, a fine adjustment of location at the boundary of 1 Tung Wan Tau Road was proposed and approved in the Baseline Monitoring Report, in order to prevent access obstruction and to minimize noise nuisance induced from HVS operation.

Remarks C:    As the agreement of ER and IEC, a fine adjustment of location at the boundary of 1 Tung Wan Tau Road was proposed and approved in the impact monitoring, in order to prevent the interruption of GI working area conducted by contractor.

 

Air Monitoring Parameters, Frequency and Duration

4.2.2.     One-hour and 24-hour TSP levels shall be measured to indicate the impacts of construction dust on air quality.

4.2.3.     24-hour TSP shall be sampled at least once in every 6 days, while sampling for 1-hour TSP shall be at least 3 times in every 6 days when the highest dust impact takes place.

 

Wind Data

4.2.4.     Hong Kong Observatory (HKO) meteorological information is widely accepted to be used in various environmental monitoring practices within HKSAR due to its professional quality and precision. Therefore, the daily wind data including Prevailing Wind Direction (degrees) and Mean Wind Speed (km/h) were obtained from Peng Chau Automatic Weather Station to serve as the representative data for meteorological condition during monitoring. The method was agreed by the IEC and approved by the ER on 4 December 2020. The representative wind data from Peng Chau Station were obtained covering the 1-hour and 24-hour TSP monitoring periods. The wind data were extracted and shown in Appendix 4.3.


 

EVENT and action plan

4.2.5.     The Action and Limit levels for construction air quality are defined in Table 4.6 and Appendix 4.1. Should non-compliance of the air quality criteria occur, action in accordance with the Event and Action Plan in Appendix 6.1 shall be carried out.

Table 4.6 Action and Limit Level for Air Quality Monitoring

Parameter

Monitoring Station

Action Level (µg/m3)

Limit Level (µg/m3)

24-hour TSP Level

AMS1

176.0

260.0

AMS2

176.0

260.0

1-hour TSP Level

AMS1

276.5

500.0

AMS2

283.7

500.0


4.3          Water Quality Monitoring

WATER QUALITY MONITORING STATIONS

4.3.1.     Water quality monitoring shall be undertaken at 7 monitoring stations in the reporting month. The proposed water quality monitoring stations of the Project are shown in Table 4.7 and Figure 4.3.

Table 4.7      Marine Water Quality Stations for Water Quality Monitoring

Station

Description

Monitoring

Period

Monitoring

Station

Easting

Northing

W1

Wang Tong River

(Major tributary)

Mid-Flood

Impact

817747

814519

Mid-Ebb

Control

W2

Wang Tong River

(Major tributary)

Mid-Flood

Impact

817775

814471

Mid-Ebb

Control

W3 *

Wang Tong River

(Minor tributary to Tai Wai Yuen)

Mid-Flood

Impact

817803

814537

Mid-Ebb

Control

W4

Wang Tong River

(Minor tributary to Tai Wai Yuen)

Mid-Flood

Impact

817825

814481

Mid-Ebb

Control

W5

Silvermine Bay

(Near Silvermine Bay Beach)

Mid-Flood

Control

817909

814452

Mid-Ebb

Impact

W6

Silvermine Bay

(Near Silvermine Bay Beach)

Mid-Flood

Control

818024

814447

Mid-Ebb

Impact

W7

Silvermine Bay

(Open Water)

Mid-Flood

Control

818061

814277

Mid-Ebb

Impact

W8

Silvermine Bay

(Open Water)

Mid-Flood

Control

818224

814444

Mid-Ebb

Impact

Remark *: Water quality monitoring at Station W3 was cancelled with verification from the IEC and approval from the EPD.

 

Water Quality Parameters, Frequency and Duration

4.3.2.     The levels of dissolved oxygen (DO), turbidity, salinity and pH shall be measured in situ while suspended solids (SS) is determined by laboratory analysis at all the designated monitoring stations.

4.3.3.     In association with the water quality parameters, other relevant data shall also be recorded, such as monitoring location / position, time, water temperature, DO saturation, weather conditions, and any special phenomena underway near the monitoring station.

4.3.4.     Impact Monitoring shall be carried out 3 days per week, at mid-flood and mid-ebb tides (within ± 1.75 hour of the predicted time). The interval between two sets of monitoring shall not be less than 36 hours. The monitoring period should avoid concurrent marine project in the vicinity.

4.3.5.     The sampling frequency of at least three days per week should be undertaken when the highest dust impact occurs. Upon completion of the construction works, the monitoring exercise at the designated monitoring locations should be continued for four weeks in the same manner as the impact monitoring. In case exceedance of Action/Limit Level is recorded, the frequency shall be increased as per the Event and Action Plan.

4.3.6.     To ensure the robustness of in-situ measurement, parameters shall be measured in duplicate. In case the difference between duplicates is larger than 25%, a third set of measurement shall be carried out.

 

EVENT and action plan

4.3.7.     The Action and Limit levels for construction water quality are defined in Table 4.9 and Appendix 4.1. Should the monitoring results of the water quality parameters at any designated monitoring station exceed the water quality criteria, action in accordance with the Event and Action Plan in Appendix 6.1 shall be carried out.

 

Table 4.9 Action and Limit Level for Water Quality Monitoring

Monitoring Station

Depth

DO (mg/L) +

Turbidity (NTU) ~

SS (mg/L) ~

Action Level

Limit Level

Action Level

Limit Level

Action Level

Limit Level

W1

Surface, Middle & Bottom

6.5

5.3

7.7 NTU or 120% of upstream control station's turbidity at the same tide of the same day, whichever is higher

12.4 NTU or 130% of upstream control station's turbidity at the same tide of the same day, whichever is higher

8.9 mg/L or 120% of upstream control station's SS at the same tide of the same day, whichever is higher

11.3 mg/L or 130% of upstream control station's SS at the same tide of the same day, whichever is higher

W2

W4

W5

Surface, Middle & Bottom

5.9

5.5

9.8 NTU or 120% of upstream control station's turbidity at the same tide of the same day, whichever is higher

10.5 NTU or 130% of upstream control station's turbidity at the same tide of the same day, whichever is higher

12.6 mg/L or 120% of upstream control station's SS at the same tide of the same day, whichever is higher

15.0 mg/L or 130% of upstream control station's SS at the same tide of the same day, whichever is higher

W6

W7

W8

Surface & Middle

Bottom

5.9

5.5

Remarks +: For DO, non-compliance occurs when monitoring results is lower than the limits.

Remarks ~: For SS and Turbidity, non-compliance occurs when monitoring results is larger than the limits

5          Monitoring Results

5.0.1      The environmental monitoring were implemented as per the environment monitoring schedules for reporting period.

 

5.1          Noise Monitoring Results

5.1.1       Noise monitoring results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.

5.1.2       No action or limit level exceedance was recorded in this reporting period.

 

5.2          Air Monitoring Results

5.2.1       Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3.

5.2.2       No action or limit level exceedance was recorded in this reporting period. 

 

5.3          Water Quality Monitoring Results

5.3.1       Water quality monitoring was conducted at seven monitoring stations three days per week in according to the schedule in the reporting. Details of water quality monitoring results and graphical presentation can be referred in Appendix 5.4.

5.3.2       Action level exceedance on turb was recorded at station W1 during mid-flood on 6 July 2022.  Investigation revealed this exceedance could be due to: Localized fluctuation in water quality due to no exceedances recorded at W4 downstream to construction site before W1; no unauthorized discharge or muddy plume observed.

5.3.3       Action level exceedance on turb was recorded at station W2 during mid-flood on 6 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation in water quality due to no exceedances recorded at W4 downstream to construction site before W2; no unauthorized discharge or muddy plume observed.

5.3.4       Action level exceedance on turb and limit level of SS were recorded at station W5 during mid-ebb on 6 July 2022. Investigation revealed this exceedance could be due to: High turbidity and SS recorded at upstream control station W4 (Turb: 24.8NTU, SS:19.0 mg/L) stirred up downstream riverbed during tidal flush.

5.3.5       Action level exceedance on DO was recorded at station W2 during mid-flood on 15 July 2022.  Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.6       Action level exceedance on DO was recorded at station W4 during mid-flood on 15 July 2022.  Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.7       Action level exceedance on DO was recorded at station W1 during mid-flood on 18 July 2022.  Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.8       Action level exceedance on DO was recorded at station W4 during mid-flood on 18 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.9       Action level exceedance on DO was recorded at station W8 Surface during mid-ebb on 20 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.10    Action level exceedance on DO was recorded at station W1 during mid-flood on 22 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.11    Action level exceedances on DO and turb were recorded at station W2 during mid-flood on 25 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed; Localized fluctuation in water quality due to no exceedances recorded at W4 downstream to construction site before W2; no unauthorized discharge or muddy plume observed.

5.3.12    Action level exceedance on DO was recorded at station W4 during mid-flood on 25 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.13    Action level exceedance on DO was recorded at station W7 during mid-ebb on 25 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.14    Action level exceedance on DO was recorded at station W8 Surface during mid-ebb on 25 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.15    Action level exceedance on DO was recorded at station W2 during mid-flood on 27 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.16    Action level exceedances on DO and turb were recorded at station W4 during mid-flood on 27 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed; Localized fluctuation around baseline turb range; unlikely contributed by solid materials from construction works; extremely high water level observed during monitoring.

5.3.17    Action level exceedance on DO was recorded at station W7 during mid-ebb on 27 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.18    Action level exceedance on DO was recorded at station W8 Surface during mid-ebb on 27 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.19    Action level exceedance on DO was recorded at station W8 Bottom during mid-ebb on 27 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.20    Action level exceedances on DO and turb were recorded at station W2 during mid-flood on 29 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed; Localized fluctuation around baseline DO range; no river channel blockage was observed; Relatively higher turbidity recorded at upstream control station W4 (Turb: 12.1 NTU) whereas no SS exceedance recorded; unlikely contributed by solid materials from construction works.

5.3.21    Action level exceedances on DO, turb and SS were recorded at station W4 during mid-flood on 29 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed; Localized fluctuation around baseline turb and SS range; extremely high water level observed during monitoring and SS could be contributed by turbulence stirring up riverbed precipitate during tidal flush; unlikely contributed by solid materials from construction works.

5.3.22    Action level exceedance on DO was recorded at station W7 during mid-ebb on 29 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.23    Action level exceedance on DO was recorded at station W8 Bottom during mid-ebb on 27 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.24    Limit level exceedance on SS was recorded at station W5 during mid-ebb on 5 Aug 2022.  Investigation revealed this exceedance could be due to: Relatively high SS recorded at upstream control station W4 (SS:14.0 mg/L); Muddy water discharging from upstream control station W4 and rain water disturbing the river water current may increase the downstream SS level at downstream monitoring station W5.

5.3.25    Action level exceedance on DO and Turb were recorded at station W1 and W2 during mid-flood on 12 Aug 2022. Investigation revealed these exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed; Cloudy water may be the cause of the increase of turb level; unlikely contributed by solid materials from construction works.

5.3.26    Action level exceedance on DO were recorded at station W2 and W8 Bottom during mid-flood and mid-ebb respectively on 15 Aug 2022. Investigation revealed these exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.27    Action level exceedance on DO were recorded at station W1, W4 during mid-flood and W7 during mid-ebb on 22 Aug 2022. Investigation revealed these exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.28    Action level exceedance on DO were recorded at station W4 and W8 Bottom during mid-flood and mid-ebb respectively on 26 Aug 2022. Investigation revealed these exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.29    Action level exceedance on DO were recorded at station W6, W7, W8 Surface and W8 Bottom during mid-ebb on 29 Aug 2022. Investigation revealed these exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.30    Action level exceedance on DO was recorded at station W7 during mid-ebb on 31 Aug 2022. Investigation revealed these exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.31    Action level exceedances on DO was recorded at station W2 and W4 during mid-flood on 5 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.32    Action level exceedance on SS was recorded at station W7 during mid-ebb on 5 Sep 2022. Investigation revealed this exceedance could be due to: High waves was observed at near shore sampling location W7 during mid-ebb. Water current may stir up the sea shore and sea bed sediment and cause the exceedance.

5.3.33    Action level exceedances on DO was recorded at station W2 and W4 during mid-flood on 7 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.34    Action level exceedances on DO was recorded at station W5, W6, W7 and W8 Surface during mid-ebb on 7 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.35    Action level exceedances on DO was recorded at station W1, W2 and W4 during mid-flood on 9 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.36    Limit level exceedance on SS was recorded at station W1 during mid-flood on 9 Sep 2022. Investigation revealed this exceedance could be due to: Special localized extreme water quality due to no Turb or SS exceedances recorded before W1; muddy river water flow was observed at the upper end of the river after W2 during mid-flood may cause the exceedance of SS at W1.

5.3.37    Action level exceedances on DO was recorded at station W5, W6, W7, W8 Surface and W8 Bottom during mid-ebb on 9 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.38    Action level exceedances on DO was recorded at station W2 and W4 during mid-flood on 13 Sep 2022. Action level exceedances on Turb was recorded at station W6 during mid-ebb on 13 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO and water quality range; no river channel blockage was observed; no muddy water was observed; no discharge or water leakage from the construction site was observed.

5.3.39    Limit level exceedances on Turb was recorded at station W5, W6, W7 and W8 Surface during mid-ebb on 15 Sep 2022. Investigation revealed this exceedance could be due to: Extreme low water level was observed from the upstream; yellow-ish pigment was observed during mid-ebb at the open water (from W5 to W8); no discharge or leakage from the construction site was found.

5.3.40    Limit level exceedances on Turb was recorded at station W5 during mid-ebb on 17 Sep 2022. Investigation revealed this exceedance could be due to: Yellow-ish pigment from the previous event was still observed and accumulated at shallow water area (W5); no discharge or leakage from the construction site was found.

5.3.41    Action level exceedances on DO at W1 and W4; action level exceedance on Turb at W2; limit level on SS at W4 was observed during mid-flood on 19 Sep 2022. Action level on Turb and limit level on SS was recorded at W6 during mid-ebb on 19 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed; significant amount of foams was observed at near-shore areas and may cause the exceedance for Turb and SS; no discharge or water leakage from the construction site was observed.

5.3.42    Action level exceedances on DO was recorded at station W2 and W7 during mid-flood and mid-ebb respectively on 21 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.43    Action level exceedance on DO was recorded at station W8 Bottom during mid-ebb on 26 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

5.3.44    Action level exceedance on DO was recorded at station W8 Bottom during mid-ebb on 26 Sep 2022. Investigation revealed this exceedance could be due to: Strong monsoon signal was on and the strong wind may produce strong under-surface current which stir up the sediment at the sea floor, causing slightly high SS level at W8 Bottom.

 

Table 5.1     Summary of Water Quality Exceedances (July)

 

Parameter

DO (S&M)

DO (Bottom)

Turbidity

SS

Exceedance count

Station

Level exceeded

Mid Ebb

Mid Flood

Mid Ebb

Mid Flood

Mid Ebb

Mid Flood

Mid Ebb

Mid Flood

Mid Ebb

Mid Flood

W1

Action

N/A

18/07/22

22/07/22

N/A

-

N/A

06/07/22

N/A

-

N/A

3

 

Limit

N/A

-

N/A

-

N/A

-

N/A

-

N/A

-

W2

Action

N/A

15/07/22

25/07/22

27/07/22

29/07/22

N/A

-

N/A

06/07/22

25/07/22

29/07/22

N/A

-

N/A

7

 

Limit

N/A

-

N/A

-

N/A

-

N/A

-

N/A

-

W4

Action

N/A

15/07/22

18/07/22

25/07/22

27/07/22

29/07/22

N/A

-

N/A

27/07/22

29/07/22

N/A

29/07/22

N/A

8

 

Limit

N/A

-

N/A

-

N/A

-

N/A

-

 N/A

-

W5

Action

-

N/A

-

N/A

06/07/22

N/A

-

N/A

1

N/A

 

Limit

-

N/A

-

N/A

-

N/A

06/07/22

N/A

1

N/A

W6

Action

29/07/22

N/A

-

N/A

-

N/A

-

N/A

1

N/A

 

Limit

-

N/A

-

N/A

-

N/A

-

N/A

-

N/A

W7

Action

25/07/22

27/07/22

29/07/22

N/A

-

N/A

-

N/A

-

N/A

3

N/A

 

Limit

-

N/A

-

N/A

-

N/A

-

N/A

-

N/A

W8

Action

20/07/22

25/07/22

27/07/22

N/A

27/07/22

29/07/22

N/A

-

N/A

-

N/A

5

N/A

 

Limit

-

N/A

-

N/A

-

N/A

-

N/A

-

N/A

Total

Action

7

11

2

0

1

6

0

1

10

18

 

Limit

0

0

0

0

0

0

1

0

1

0

 

Table 5.2     Summary of Water Quality Exceedances (August)

 

Parameter

DO (S&M)

DO (Bottom)

Turbidity

SS

Exceedance count

Station

Level exceeded

Mid Ebb

Mid Flood

Mid Ebb

Mid Flood

Mid Ebb

Mid Flood

Mid Ebb

Mid Flood

Mid Ebb

Mid Flood

W1

Action

N/A

12/08/22

22/08/22

N/A

-

N/A

12/08/22

N/A

-

N/A

3

 

Limit

N/A

-

N/A

-

N/A

-

N/A

-

N/A

-

W2

Action

N/A

12/08/22

15/08/22

N/A

-

N/A

12/08/22

N/A

-

N/A

3

 

Limit

N/A

-

N/A

-

N/A

-

N/A

-

N/A

-

W4

Action

N/A

22/08/22

26/08/22

N/A

-

N/A

-

N/A

-

N/A

2

 

Limit

N/A

-

N/A

-

N/A

-

N/A

-

 N/A

-

W5

Action

-

N/A

-

N/A

-

N/A

-

N/A

-

N/A

 

Limit

-

N/A

-

N/A

-

N/A

05/08/22

N/A

1

N/A

W6

Action

29/08/22

N/A

-

N/A

-

N/A

-

N/A

1

N/A

 

Limit

-

N/A

-

N/A

-

N/A

-

N/A

-

N/A

W7

Action

22/08/22

29/08/22

31/08/22

N/A

-

N/A

-

N/A

-

N/A

3

N/A

 

Limit

-

N/A

-

N/A

-

N/A

-

N/A

-

N/A

W8

Action

29/08/22

N/A

15/08/22

26/08/22

29/08/22

N/A

-

N/A

-

N/A

4

N/A

 

Limit

-

N/A

-

N/A

-

N/A

-

N/A

-

N/A

Total

Action

5

6

3

0

0

2

0

0

8

8

 

Limit

0

0

0

0

0

0

1

0

1

0

 

Table 5.3     Summary of Water Quality Exceedances (September)

 

Parameter

DO (S&M)

DO (Bottom)

Turbidity

SS

Exceedance count

Station

Level exceeded

Mid Ebb

Mid Flood

Mid Ebb

Mid Flood

Mid Ebb

Mid Flood

Mid Ebb

Mid Flood

Mid Ebb

Mid Flood

W1

Action

N/A

09/09/22

19/09/22

N/A

N/A

N/A

-

N/A

-

N/A

2

 

Limit

N/A

-

N/A

N/A

N/A

-

N/A

09/09/22

N/A

1

W2

Action

N/A

05/09/22

07/09/22

09/09/22

13/09/22

21/09/22

N/A

N/A

N/A

19/09/22

N/A

-

N/A

6

 

Limit

N/A

-

N/A

N/A

N/A

-

N/A

-

N/A

-

W4

Action

N/A

05/09/22

07/09/22

09/09/22

13/09/22

19/09/22

N/A

N/A

N/A

-

N/A

-

N/A

5

 

Limit

N/A

-

N/A

N/A

N/A

-

N/A

19/09/22

N/A

1

W5

Action

07/09/22

09/09/22

N/A

-

N/A

-

N/A

-

N/A

2

N/A

 

Limit

-

N/A

-

N/A

15/09/22

17/09/22

N/A

-

N/A

2

N/A

W6

Action

07/09/22

09/09/22

N/A

-

N/A

13/09/22

19/09/22

N/A

-

N/A

4

N/A

 

Limit

-

N/A

-

N/A

15/09/22

N/A

19/09/22

N/A

2

N/A

W7

Action

07/09/22

09/09/22

21/09/22

N/A

-

N/A

-

N/A

05/09/22

N/A

4

N/A

 

Limit

-

N/A

-

N/A

15/09/22

N/A

-

N/A

1

N/A

W8

Action

07/09/22

09/09/22

N/A

09/09/22

26/09/22

N/A

-

N/A

28/09/22

N/A

5

N/A

 

Limit

-

N/A

-

N/A

15/09/22

N/A

-

N/A

1

N/A

Total

Action

9

12

2

-

2

1

2

-

15

13

 

Limit

-

-

-

-

5

-

1

2

6

2

 

 

5.4          Waste Management

5.4.1      The quantities of waste for disposal in the Reporting Period are summarized in Table 5.1 and Table 5.2.


 

Table 5.3 Summary of Quantities of Inert C&D Materials

Waste Type

Quantity

(this period)

Quantity

(Project commencement to the end of the last quarter)

Cumulative Quantity-to-Date

Hard Rock and Large Broken Concrete (Inert)

(in ‘000m3)

0

0.007

0.007

Reused in this Contract (Inert)

(in ‘000m3)

0

0

0

Reused in other Projects (Inert)

(in ‘000m3)

0

0

0

Disposal as Public Fill (Inert)

(in ‘000m3)

0.315

0.039

0.354

 

Table 5.4 Summary of Quantities of C&D Wastes

Waste Type

Quantity

(this quarter)

Quantity

(Project commencement to the end of last quarter)

Cumulative Quantity-to-Date

Metals (in ‘000kg)

0

0

0

Paper / Cardboard Packing

(in ‘000kg)

0

0

0

Plastics

(in ‘000kg)

0

0.03

0.03

Chemical Wastes

(in ‘000kg)

0

0

0

General Refuses

(in ‘000m3)

0.0672

0.051

0.1182

 

 

6          Compliance Audit

6.1          Noise Monitoring.

6.1.1   No action or limit level exceedance was recorded in this reporting period.

 

6.2          Air Quality Monitoring

6.2.1       No action or limit level exceedance was recorded in this reporting period.

 

6.3          Water Quality Monitoring

6.3.1       Action level exceedance on turb was recorded at station W1 during mid-flood on 6 July 2022.  Investigation revealed this exceedance could be due to: Localized fluctuation in water quality due to no exceedances recorded at W4 downstream to construction site before W1; no unauthorized discharge or muddy plume observed.

6.3.2       Action level exceedance on turb was recorded at station W2 during mid-flood on 6 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation in water quality due to no exceedances recorded at W4 downstream to construction site before W2; no unauthorized discharge or muddy plume observed.

6.3.3       Action level exceedance on turb and limit level of SS were recorded at station W5 during mid-ebb on 6 July 2022. Investigation revealed this exceedance could be due to: High turbidity and SS recorded at upstream control station W4 (Turb: 24.8NTU, SS:19.0 mg/L) stirred up downstream riverbed during tidal flush.

6.3.4       Action level exceedance on DO was recorded at station W2 during mid-flood on 15 July 2022.  Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.5       Action level exceedance on DO was recorded at station W4 during mid-flood on 15 July 2022.  Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.6       Action level exceedance on DO was recorded at station W1 during mid-flood on 18 July 2022.  Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.7       Action level exceedance on DO was recorded at station W4 during mid-flood on 18 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.8       Action level exceedance on DO was recorded at station W8 Surface during mid-ebb on 20 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.9       Action level exceedance on DO was recorded at station W1 during mid-flood on 22 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.10    Action level exceedances on DO and turb were recorded at station W2 during mid-flood on 25 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed; Localized fluctuation in water quality due to no exceedances recorded at W4 downstream to construction site before W2; no unauthorized discharge or muddy plume observed.

6.3.11    Action level exceedance on DO was recorded at station W4 during mid-flood on 25 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.12    Action level exceedance on DO was recorded at station W7 during mid-ebb on 25 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.13    Action level exceedance on DO was recorded at station W8 Surface during mid-ebb on 25 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.14    Action level exceedance on DO was recorded at station W2 during mid-flood on 27 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.15    Action level exceedances on DO and turb were recorded at station W4 during mid-flood on 27 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed; Localized fluctuation around baseline turb range; unlikely contributed by solid materials from construction works; extremely high water level observed during monitoring.

6.3.16    Action level exceedance on DO was recorded at station W7 during mid-ebb on 27 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.17    Action level exceedance on DO was recorded at station W8 Surface during mid-ebb on 27 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.18    Action level exceedance on DO was recorded at station W8 Bottom during mid-ebb on 27 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.19    Action level exceedances on DO and turb were recorded at station W2 during mid-flood on 29 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed; Localized fluctuation around baseline DO range; no river channel blockage was observed; Relatively higher turbidity recorded at upstream control station W4 (Turb: 12.1 NTU) whereas no SS exceedance recorded; unlikely contributed by solid materials from construction works.

6.3.20    Action level exceedances on DO, turb and SS were recorded at station W4 during mid-flood on 29 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed; Localized fluctuation around baseline turb and SS range; extremely high water level observed during monitoring and SS could be contributed by turbulence stirring up riverbed precipitate during tidal flush; unlikely contributed by solid materials from construction works.

6.3.21    Action level exceedance on DO was recorded at station W7 during mid-ebb on 29 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.22    Action level exceedance on DO was recorded at station W8 Bottom during mid-ebb on 27 July 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.23    Limit level exceedance on SS was recorded at station W5 during mid-ebb on 5 Aug 2022.  Investigation revealed this exceedance could be due to: Relatively high SS recorded at upstream control station W4 (SS:14.0 mg/L); Muddy water discharging from upstream control station W4 and rain water disturbing the river water current may increase the downstream SS level at downstream monitoring station W5.

6.3.24    Action level exceedance on DO and Turb were recorded at station W1 and W2 during mid-flood on 12 Aug 2022. Investigation revealed these exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed; Cloudy water may be the cause of the increase of turb level; unlikely contributed by solid materials from construction works.

6.3.25    Action level exceedance on DO were recorded at station W2 and W8 Bottom during mid-flood and mid-ebb respectively on 15 Aug 2022. Investigation revealed these exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.26    Action level exceedance on DO were recorded at station W1, W4 during mid-flood and W7 during mid-ebb on 22 Aug 2022. Investigation revealed these exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.27    Action level exceedance on DO were recorded at station W4 and W8 Bottom during mid-flood and mid-ebb respectively on 26 Aug 2022. Investigation revealed these exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.28    Action level exceedance on DO were recorded at station W6, W7, W8 Surface and W8 Bottom during mid-ebb on 29 Aug 2022. Investigation revealed these exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.29    Action level exceedance on DO was recorded at station W7 during mid-ebb on 31 Aug 2022. Investigation revealed these exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.30    Action level exceedances on DO was recorded at station W2 and W4 during mid-flood on 5 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.31    Action level exceedance on SS was recorded at station W7 during mid-ebb on 5 Sep 2022. Investigation revealed this exceedance could be due to: High waves was observed at near shore sampling location W7 during mid-ebb. Water current may stir up the sea shore and sea bed sediment and cause the exceedance.

6.3.32    Action level exceedances on DO was recorded at station W2 and W4 during mid-flood on 7 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.33    Action level exceedances on DO was recorded at station W5, W6, W7 and W8 Surface during mid-ebb on 7 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.34    Action level exceedances on DO was recorded at station W1, W2 and W4 during mid-flood on 9 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.35    Limit level exceedance on SS was recorded at station W1 during mid-flood on 9 Sep 2022. Investigation revealed this exceedance could be due to: Special localized extreme water quality due to no Turb or SS exceedances recorded before W1; muddy river water flow was observed at the upper end of the river after W2 during mid-flood may cause the exceedance of SS at W1.

6.3.36    Action level exceedances on DO was recorded at station W5, W6, W7, W8 Surface and W8 Bottom during mid-ebb on 9 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.37    Action level exceedances on DO was recorded at station W2 and W4 during mid-flood on 13 Sep 2022. Action level exceedances on Turb was recorded at station W6 during mid-ebb on 13 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO and water quality range; no river channel blockage was observed; no muddy water was observed; no discharge or water leakage from the construction site was observed.

6.3.38    Limit level exceedances on Turb was recorded at station W5, W6, W7 and W8 Surface during mid-ebb on 15 Sep 2022. Investigation revealed this exceedance could be due to: Extreme low water level was observed from the upstream; yellow-ish pigment was observed during mid-ebb at the open water (from W5 to W8); no discharge or leakage from the construction site was found.

6.3.39    Limit level exceedances on Turb was recorded at station W5 during mid-ebb on 17 Sep 2022. Investigation revealed this exceedance could be due to: Yellow-ish pigment from the previous event was still observed and accumulated at shallow water area (W5); no discharge or leakage from the construction site was found.

6.3.40    Action level exceedances on DO at W1 and W4; action level exceedance on Turb at W2; limit level on SS at W4 was observed during mid-flood on 19 Sep 2022. Action level on Turb and limit level on SS was recorded at W6 during mid-ebb on 19 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed; significant amount of foams was observed at near-shore areas and may cause the exceedance for Turb and SS; no discharge or water leakage from the construction site was observed.

6.3.41    Action level exceedances on DO was recorded at station W2 and W7 during mid-flood and mid-ebb respectively on 21 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.42    Action level exceedance on DO was recorded at station W8 Bottom during mid-ebb on 26 Sep 2022. Investigation revealed this exceedance could be due to: Localized fluctuation around baseline DO range; no river channel blockage was observed.

6.3.43    Action level exceedance on DO was recorded at station W8 Bottom during mid-ebb on 26 Sep 2022. Investigation revealed this exceedance could be due to: Strong monsoon signal was on and the strong wind may produce strong under-surface current which stir up the sediment at the sea floor, causing slightly high SS level at W8 Bottom.

 

6.4          Summary of Exceedance

6.4.1       The Event Action Plan for construction noise, air quality and water quality are presented in Appendix 6.1.

6.4.2       The summary of exceedance is presented in Appendix 6.2.

 

6.5          Environmental Site Audit

6.5.1       During the reporting period, the Environmental Team (ET) conducted weekly site inspections and IEC attended the joint site inspection monthly.

6.5.2       During this reporting month, monthly landscape site audits were conducted monthly.

6.5.3       No non-compliance was found during the site inspection while reminders on environmental measures were recommended.

 

6.6          Review of the Reasons for and the Implications of Non-compliance

6.6.1       No environmental non-compliance was recorded in the reporting period.

 

6.7          Summary of action taken in the event of and follow-up on non-compliance

6.7.1       There was no particular action taken since no non-compliance was recorded in the reporting period.

 

7          Complaints, Notification of Summons and Prosecution

7.0.1.     No environmental complaint, notification of summons and successful prosecution regarding construction works was recorded in the reporting period.

7.0.2.     The details of cumulative complaint log and updated summary of complaints are presented in Appendix 8.1.

7.0.3.     Cumulative statistic on complaints and successful prosecutions are summarized in Table 8.1 and Table 8.2 respectively.

Table 8.1 Cumulative Statistics on Complaints

Reporting Period

No. of Complaints

July 2022 – September 2022

0

Project commencement to the end of last reporting month

-

Total

0

 

Table 8.2 Cumulative Statistics on Successful Prosecutions

Environmental Parameters

Cumulative No. Brought Forward

No. of Successful Prosecutions this month (Offence Date)

Cumulative No. Project-to-Date

Air

-

0

0

Noise

-

0

0

Water

-

0

0

Waste

-

0

0

Total

-

0

0

 

8          Conclusion

8.0.1.     The EM&A programme was carried out in accordance with the EM&A Manual requirements, minor alterations to the programme proposed were made in response to changing circumstances.

8.0.2.     The EM&A programme was considered effective and no change is anticipated as reviewed for this quarter.